MEASURE S and P Citywide Road Resurfacing Phase 4

MEASURE S and P Citywide Road Resurfacing Phase 4 is starting, and it includes pavement patch work this winter and a slurry seal in spring 2024 on high impact roads in Monterey, including Fremont Street, Munras Avenue, and Lighthouse Avenue. The work will be one lane closure at a time in one direction. Working hours are 8 a.m. to 5 p.m., Monday through Friday (no work on weekends or holidays). Residences and businesses directly impacted will receive printed flyers from the contractor with contact information.

See the full list of locations and street segments
Here's an updated schedule as of Oct., 19, 2023: 
  • Oct 16, 2023: Begin street improvements
  • Oct 16 - 18: Pothole for existing utilities
  • Oct 16 - Nov 3: Lower existing water valves, manholes
  • Oct 24 - Nov 2: Munras Ave, pavement patch work
  • Nov 3 - Nov 7: Fremont Ave, grind & pave
  • Nov 8: Aguajito Rd, pavement patch work
  • Nov 9: Don Dahvee Lane, pavement patch work
  • Nov 13: Alta Mesa, pavement patch work
  • Nov 13: Alta Mesa Circle, grind & pave
  • Nov 14 - 21: Lighthouse Ave, pavement patch work

streetSaver_RSRUpcoming_Oct23