Fixing Streets - Measure P

Thank you for saying yes to Measure S

Streets Status as of Oct. 2018

Measure P Street Resurfacing Status Map Measure PStreets Status as of October 2018

Streets Status for 2015 - 2019

Measure P Street Resurfacing Status Map Measure PStreets Status Map, July 2018

Fixing Streets Measure P Sign

Measure P Third Year Report

Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
JANUARY 21, 2019:

Please note: Schedule is subject to change.
  1. Recreation Trail Improvements - between Reedside and Drake (CIP)
  2. MEASURE P Signalized Intersections and ADA Improvements, Phase 3 - Potholing work continues to locate utilities on Franklin at Washington. Right turn lane closure from Franklin to Washington on Mon., 1/21.
  3. Pacific Street Sidewalk, Phase 3 - Between San Bernabe and Soledad Drive on the business-side of Pacific. Work at Via Arboles will require traffic control during work hours but no lane closures. SEE PLANS (NIP)
  4. Sewer Rehab pipe bursting - Pipe bursting underway (this process is noisy) - Mon., 1/21 on Cass at El Dorado. Work hours 7 AM to 7 PM  SEE MAP | SEE SCHEDULE ("What a Relief")
  5. Waterfront Parking Lot Upgrades - Large equipment and lots of activity this week to prepare for paving on Fri., 1/25 - reconfiguring, repaving, and added infrastructure including electric vehicle charging stations SEE SCHEDULE | NEWS RELEASE (CIP and Parking Fund)
  6. MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 2 - Work at Munras and El Dorado will last 3 - 4 days; more work coming in the following weeks at the Del Monte and English intersection, Del Monte and Cunningham (the NPS Gate intersection), and at the two entrances to Del Monte Center.
  7. MEASURE P Citywide ADA Ramps and Streets Reconstruction, Phase 7 - Finish final markings/punch list items on El Dorado, Casanova, and in Fisherman's Flats. Weather impacted this work being completed.
  8. CONA Park Improvements New playground (SEE GRAPHIC) and ADA Improvements - SCHEDULE (NIP)
  9. North Fremont Bike and Pedestrian Access and Safety Improvement Project - The schedule next week is to machine pour the bike path as follows…
    - 1/22: Dry run machine/prep machine - EB N. Fremont (toward Seaside) may be restricted to 1 lane for the dry run - short timeframe, mid-morning and only if needed
    - 1/23: Machine pour EB N. Fremont (toward Seaside) - EB N. Fremont will be 1 lane all day
    - 1/24: Machine pour WB N. Fremont (toward Monterey) - no additional closure required - WB N. Fremont will remain 1 lane
    - 1/25: Finish machine pour WB N. Fremont (only if unable to finish on 1/23)
    There will be minor TC/flagging operations intermittently to allow concrete trucks to enter/exit the closure on both pour days, as well as flagging operations through the intersections as needed when the machine needs to cross the roadway. Other Work: NW & SW corners of Fremont at Casa Verde (electrical & concrete) will continue on for the two weeks. Restoring of lanes expected by the first week in February. There will still be traffic control/lane restrictions required for work at Casanova, Ramona & Airport/Dela Vina. For more information please see the FACT SHEET - NO WORK ON WEEKENDS. PLEASE SUPPORT AREA BUSINESSES. Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates
  10. Cal-Am Cannery Row waterline project: Crews anticipate finishing this section of the project early in the week, which will mark completion of the 8 inch main pipe installation. The next phase will be to begin heading back toward the Aquarium on Drake to extend service laterals – the smaller pipes that will come off the new main and connect to individual businesses. The traffic pattern for the coming phase will be similar to what was used to date; however, impacted lanes will alternate as work crosses the road. Work hours are 8 AM to 5 PM weekdays. See Cal-Am letter for details (Non-City Project)

construction signs

Ongoing

  1. Waterfront Parking Lot Upgrades - Please check the Current list of projects for details.
  2. Measure P Citywide Street Resurfacing, Phase 7 - Final slurry deferred to April, 2019 due to scheduling and weather conflicts. Crews throughout Camino Aguajito, Camino El Estero, Del Monte Ave, and Pacific adding temporary markings. SEE MAP
  3. Solar Panels installation on the Monterey Conference Center - installation of 330 solar panels
  4. Monterey Bay Aquarium Education Center Construction - See recent San Jose Mercury News article - daily closures of Hoffman between Wave and Cannery Row through the end of this week. (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue. Completion expected at the end of 2018; move-in early 2019.

Upcoming

  1. Cannery Row Parking Garage Elevator Enclosure - (CIP)
  2. Montecito Park Improvements, Phase 3 (CDBG and NIP)

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Measure P Oversight Committee - see page for list of meetings
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts