Fixing Streets - Measure P

Streets Status, July 2018

Measure P Street Resurfacing Status Map Measure PStreets Status Map, July 2018

Fixing Streets Measure P Sign

Measure P Third Year Report

http://pub.lucidpress.com/86e7270c-826f-4460-acc9-9ebddbedb54a/#-C1X-CG2sX7r

Also in PDF

Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
SEPTEMBER 17:

Please note: The schedule is subject to change.
  • Measure P Citywide Street Resurfacing, Phase 7- high impact areas including Del Monte, Pacific and Aguajito - SEE MAP - This week, preparations for work starting on the week of September 24 will include markings and exploratory digging.
  • Breakwater Bathroom ADA Upgrades, Phase 2 - This phase includes the reconstruction of the ADA parking spaces in front of the building. This work will require shutting down access to the women's side of the restroom facilities, however additional portable toilets brought in during the work. Completion of this work expected by the end of Sep. - (NIP)
  • Cal-Am Cannery Row waterline project - Preliminary exploratory digging this week may impact traffic and parking, but no closures planned.See Cal-Am letter for details (Non-City Project)
  • Measure P Citywide ADA Ramps and Streets Reconstruction, Phase 7 Fisherman's Flats: Final stages of construction on Marsala, Trapani, and San Vito; Villa del Monte: ADA sidewalk intersection work on Encina at Dela Vina. Expect road closures. Businesses open. See schedule
  • North Fremont Bike and Pedestrian Access and Safety Improvement Project - Temporary striping has been completed.  K-rail will be set on Wed/Thurs of this week. N Fremont EB (toward Seaside): Lane shifts at Casa Verde - 2 lanes EB Casa Verde to Casanova plus left turns available at intersections – no street parking. N Fremont WB (toward Monterey): Lane shift at Casanova - 1 lane WB Casanova to Casa Verde plus left turns at intersections – no street parking.
    Alternate route recommended during peak hours. Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates
  • MEASURE P CitywideStreet Resurfacing, Phase 6 - MAP Final markings to finish - no detours in effect
  • Measure P Citywide ADA Ramps and Streets Reconstruction, Phase 6 - Cal-Am work on the 100 and 200 blocks of Via Gayuba. Water line repairs continue on 100 block. Full closures may be in effect daily after school drop off time. Once that is complete, the final coat of pavement (late-Sep) will be done and the NIP-funded crosswalk will be next. Striping still pending on York Road and Perry Lane (nightwork).
  • 200- 300 block of English Avenue - Final preparations for paving on the week of September 24. (NIP)
  • Colton Hall ADA Improvements - Hand rail installation. (Grants, NIP and CIP)
  • Cal Am Monterey Pipeline Project (Non-City Project) - SCHEDULE through September 28 -also see www.watersupplyproject.org/
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • PG&E gas line installation on Madison Street - Traffic control in place through 9/12/18, Mon through Thu, 7 AM to 5:30 PM - Madison St. from intersection of Van Buren St. to Pacific St. On Pacific St. From Madison St to Logan Ln. (Non-City Project)

construction signs

Upcoming

  1. Solar Panels installation at Monterey Conference Center- fall
  2. MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 2 -- details coming soon
  3. Sidewalk repair - Brick paver work on Del Monte at the Marriott and at 470 Tyler Street. - (CIP Sidewalk Fund)
  4. Waterfront Parking Lot- reconfiguring, repaving, and added infrastructure including electric vehicle charging stations
  5. Sewer Rehabilitation Project Phase 3-5-6- final phase of "What a Relief" sewer rehabilitation project - learn more at https://monterey.org/City-Hall/Featured-Projects/Fixing-Sewers
  6. Pacific Street Sidewalk, Phase 3- (NIP)
  7. Monterey Mural reinstallation on Monterey Conference Center.

Ongoing

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Measure P Oversight Committee - see page for list of meetings
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts