Fixing Streets - Measure S

As of April 1, 2019 - Measure P is now Measure S

Thank You!

Streets Status for 2019

Measure P and S Street Resurfacing Status Map Measure SStreets Status for 2019

Fixing Streets Measure S Sign

Measure P 2015 - 2019

Measure P Third Year Report

Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Fun Facts


Week beginning
July 15, 2019:

Active Engineering Projects Schedule
Please note: Schedule is subject to change.

Special Event Notice: From 3:00 to 10:00 PM on Saturday, July 13th, Cannery Row will be closed to all traffic from Drake to David for their 22nd Annual Race Night on the Row.

  1. MEASURE S Barnet Segal Lane Repaving Project- Paving continued into Wed., 7/17. Barnet Segal will remain closed until next Thursday 7/18. Access to the Westland House is available via Iris Canyon.
  2. Doud Street Sewer Repair- Road opening - final patch paving coming soon.
  3. Gigling Road ADA Ramps - At the Arnhem and Parker Flats Cutoff roads intersections. Traffic may be impacted. (Presidio)
  4. Glenwood Bus Stop and Crosswalk Improvement - Traffic impacts include one way traffic and some detours during work hours. Project will last until about mid-August. See page 42 - https://monterey.org/Portals/0/Reports/NIP/NIP-Manual-2016.pdf and Item 14, https://monterey.org/Portals/0/Reports/NIP/NIP-FY17-18-Approved-Projects.pdf (NIP)
  5. Sewer Rehab pipe bursting - The two remaining locations, Wharf 2 and the Munras onramp to Highway 1 South, will be done by the end of July. More details coming soon. ("What a Relief")
  6. North Fremont Bike and Pedestrian Access and Safety Improvement Project - on schedule to finish by the end of August - more details coming soon.
    For more information please see the FACT SHEET Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates

construction signs

Ongoing

  1. None at this time

Upcoming

  1. Wayfinding Signage Project (CIP)
  2. MEASURE S Street Improvements - Potholing on Mar Vista for future street repairs that will start in a few months.
  3. Sewer Lining Project (Sewer CIP Repair Fund)
  4. Cannery Row Parking Garage Elevator Enclosure Scheduled for fall 2019 - (CIP)

CalTrans may be performing other work locally. Look up CalTrans construction.

Measure S Tax Quick Facts

Thank you for saying yes to Measure S