Fixing Streets - Measure P

Streets Status as of Oct. 2018

Measure P Street Resurfacing Status Map Measure PStreets Status as of October 2018

Streets Status for 2015 - 2019

Measure P Street Resurfacing Status Map Measure PStreets Status Map, July 2018

Fixing Streets Measure P Sign

Measure P Third Year Report

Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
NOVEMBER 12:

Please note: The schedule is subject to change.
  • Measure P Citywide ADA Ramps and Streets Reconstruction, Phase 7 - Alta Mesa Neighborhood: El Dorado St. at Via Mirada. Work includes electrical, street lighting on El Dorado and a new median. Not included: ADA ramps - starts Nov. 13. Casanova Oak Knoll Neighborhood: Casanova from Fremont to Euclid paving scheduled for Nov. 26 and will last about four days. Work includes street reconstruction, but no intersection ADA sidewalk ramps. Access will be very limited and only for residents and emergency vehicles. Residents with special access requests should call the Engineering Office at (831) 646-3997.
  • MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 2 - Munras from El Dorado to Buena Vista (at the Del Monte Center entrances.) - Ramp work starts this week - may reduce/narrow lane access entering and exiting Del Monte Center at main entrance.
  • Measure P Citywide Street Resurfacing, Phase 7 - Final slurry deferred to April, 2019 due to scheduling and weather conflicts. Crews throughout Camino Aguajito, Camino El Estero, Del Monte Ave, and Pacific adding temporary markings. SEE MAP
  • North Fremont Bike and Pedestrian Access and Safety Improvement Project Traffic control and lane closures will remain the same. For more information please see the OCT 2018 PROGRESS REPORT and FACTS SHEET - Alternate route recommended during peak hours. NO WORK ON WEEKENDS. PLEASE SUPPORT AREA BUSINESSES. Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates
  • Monterey Mural re-installation on the Monterey Conference Center - Ribbon-cutting rededication event on Thursday, November 29 at 2 p.m. Details posted soon.
  • Cal-Am Cannery Row waterline project - Tue., 11/13: In the early morning Cal-Am will institute single direction traffic control on Cannery Row (towards the Aquarium). This will remain in effect during the course of the project. They will also mobilize equipment and set up staging and final traffic barricades. Wed., 11/14: Cal-Am begins excavating for the new pipeline starting mid-block between Hoffman and Prescott. This part of the project will proceed towards the Aquarium and continue through the remainder of the year. Connecting businesses to the new main should take place in early 2019.
    Work hours are 8 AM to 5 PM. See Cal-Am letter for details (Non-City Project)

construction signs

Upcoming

  1. CONA Park Improvements - (NIP)
  2. Waterfront Parking Lot Upgrades - reconfiguring, repaving, and added infrastructure including electric vehicle charging stations - starting week of Nov. 19 (CIP)
  3. Pacific Street Sidewalk, Phase 3 - (NIP)
  4. Sewer Rehab pipe bursting - ("What a Relief")

Ongoing

  • Solar Panels installation on the Monterey Conference Center - installation of 330 solar panels
  • Monterey Bay Aquarium Education Center Construction - daily closures of Hoffman between Wave and Cannery Row through the end of this week. (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue. Completion expected at the end of 2018; move-in early 2019.

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Measure P Oversight Committee - see page for list of meetings
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts