Fixing Streets - Measure P


Presentation to City Council at the February 20, 2018 meeting - Measure P History, Progress and Options to Renew - available in PDF, and also on video-on-demand (beginning at 30 minutes).


Streets Completed, as of Dec. 2017

Measure P Street Resurfacing Status Map Measure PProject Status Map, Dec. 2017

Fixing Streets Measure P Sign

Measure P Second Year Report

Second Year Report | PDF Version

First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
April 23:

Please note: The schedule is subject to change.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Breakwater Restroom ADA Upgrades - from April 9 - May 24 - one external shower will remain operational and there will be a portable restroom available (CIP)
  • Cannery Row Parking Lot 7 ADA Upgrades - Cannery Row at David Avenue - half the lot will remain open at a time, April 9 - May 25
  • Skyline Forest Drive to Mar Vista Drive - Road closure, Apr. 23 through 26, from 7 AM to 7 PM. Northbound Lane Closure Apr. 27, 7 AM to 7 PM. Resident access and Officers and Flagmen present to help traffic flow. SEE MAPS (and please note the dates are 4/23 - 4/26)
  • 200- 300 block of English Avenue - install new curbs, sidewalks, drains, and gutters (NIP)
  • Moon bridge repair at Dennis the Menace Playground - finishing touches done this week (NIP)
  • Colton Hall ADA Improvements - work will impact parking in the Dutra lot - NEWS RELEASE (Grants, NIP and CIP)
  • MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 1 - Impacting the following intersections: Pacific at Soledad; Pacific at El Dorado; Pacific at Jefferson; Pacific at Franklin; Franklin at Van Buren; Franklin at Monroe; and Del Monte at Tyler - PARTIAL SCHEDULE
  • Montecito Park Entry and Seating Installation and Phase 2 Site Improvements Project (NIP and CDBG)
  • Stuart Avenue closure (Casanova Oak Knoll neighborhood) - PG&E to move a pole and then work can be completed later in April. (NIP)
  • Wharf II Pile Replacement & Repair - Critical repairs - traffic and parking may be impacted. (CIP)
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Pipeline work will continue along Mark Thomas Road and on the Highway 68 pipe bridge at Old Salinas Highway and Fairgrounds Road, Monday through Friday, 7 a.m. to 5 p.m. Traffic controls will be posted, including the Aguajito Road/Mark Thomas Drive detours. No road closures are anticipated this week due to the bridge construction.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays through Fall 2018 - Tentative closure dates:
    4/24: morning closure for material offhaul;
    4/27: morning closure for material offhaul.

construction signs

Upcoming

  1. Measure P Citywide ADA Ramps and Streets Reconstruction, Phase 6 - Via Gayuba, York Road, Perry Lane, and Vets Park Campsite - early June start date
  2. Citywide sewer spot repairs, includes David Avenue at Jessie Street- see map - (sewer fund and "What a Relief")
  3. Scholze Community Center parking lot- coming in June
  4. North Fremont Bike and Pedestrian Access and Safety Improvement Project - Currently out to bid - learn more about this project: monterey.org/NFremontBikePed and sign up for email updates.

Ongoing

  • Cooper Molera Adobe State Historical Park, Polk and Munras (Non-City Project) This project may impact parking and traffic in the area at times. Expected completion in Spring 2018.
  • Van Buren Senior Housing Project Van Buren Senior Housing is the result of a partnership between the City of Monterey and MidPen Housing to bring much needed affordable senior housing to the city. Van Buren is ideally situated in downtown Monterey – only a short walk from parks, a library, a major regional transit center, a large grocery store, and various other amenities. Van Buren began construction in April 2017 and is expected to welcome residents in summer 2018.

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Measure P Oversight Committee - see page for list of meetings
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts