Fixing Streets - Measure S

As of April 1, 2019 - Measure P is now Measure S

Thank You!

Streets Status for 2019

Measure P and S Street Resurfacing Status Map Measure SStreets Status for 2019

Fixing Streets Measure S Sign

Measure P 2015 - 2019

Measure P Third Year Report

Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Fun Facts


Weeks beginning
APRIL 15, 2019:

Active Engineering Projects Schedule
Please note: Schedule is subject to change.
  1. Crosswalk at Hoffman and Cannery Row Scheduled to begin around Apr. 22 - see NIP Project on page 79 - (NIP)
  2. Skyline Curb and Gutter Repairs Stratford Place and Victoria Rise - (NIP)
  3. Measure P Citywide Street Resurfacing, Phase 7 - April 12 and 15: Iris Canyon from Glenwood to Don Dahvee as well as Barnet Segal Lane between Highway 1 and Iris Canyon. Scheduled coming soon - Tentatively scheduled to start week of Apr. 22: Crews throughout Pacific St. From Scott to El Dorado; Aguajito Rd. From Del Monte to Fremont; Camino El Estero From Del Monte to Fremont; Del Monte from Camino El Estero to Roberts (East End) - to prepare for slurry SEE MAP
  4. Measure P Citywide ADA Ramps and Street Reconstruction Phase 7- Drainage and street improvements at the intersection of Via Mirada and El Dorado. This project is delayed due to work crews working on the Waterfront Lot and on Glenwood Circle.
  5. CR7 Parking Lot - lot at David/Irving/Foam - Phase 2 - Final patch paving (CIP)
  6. Madison Street ADA Ramps and Montecito Park Improvements, Phase 3 - Construction continues on Madison between Dutra and Van Buren. Concrete work near the Police Dept Offices next week. Traffic control will be in place on Madison. (CDBG and NIP)
  7. Pacific Street Sidewalk, Phase 3 - Final work on the retaining wall. SEE PLANS (NIP)
  8. Sewer Rehab pipe bursting - Pipe bursting underway (this process is noisy). SEE MAP | NEW 3 WEEK SCHEDULE ("What a Relief")
  9. Waterfront Parking Lot Upgrades - This project should be completed by mid-May. Work has moved to Phase 2 on the other side of the lot - reconfiguring, repaving, and added infrastructure including electric vehicle charging stations 3-WEEK SCHEDULE (CIP and Parking Fund)
  10. MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 2 -Final electrical work at all affected locations. - Del Monte at Cunningham, Del Monte at English, and Munras near Del Monte Center.
  11. North Fremont Bike and Pedestrian Access and Safety Improvement Project - One block of Casanova Avenue, between North Fremont and Kolb Ave, will be closed on Friday 4/12, re-opened over the weekend, and then closed for approx. three weeks starting Monday 4/15 for pedestrian improvements. Detour at Ramona Ave will be in place and Jiffy Lube access will be allowed. MARCH UPDATE - For more information please see the FACT SHEET - PLEASE SUPPORT AREA BUSINESSES. Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates
  12. Cal-Am Cannery Row waterline project: 4/15- Street restoration will begin. The east bound lane on Cannery Row between Hoffman & Prescott will close for one week allowing the concrete to cure;4/15- Fish Hopper; 4/16-711 Cannery Row domestic & fire service; 4/17-Aquarium fire service on west side of Cannery Row; 4/18-Intercontinental night work; 4/19-No work due to Thursday night work (rest period) Work hours are 8 AM to 5 PM weekdays. See Cal-Am letter for details (Non-City Project)

construction signs

Ongoing

  1. Solar Panels installation on the Monterey Conference Center - installation of 330 solar panels
  2. Monterey Bay Aquarium Education Center Construction - (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue. Completion and move-in expected by late spring 2019.

Upcoming

  1. ADA Improvements and remodel of City Clerk's Office late April start date - (CIP)
  2. Cannery Row Parking Garage Elevator Enclosure Scheduled for fall 2019 - (CIP)

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Measure P Oversight Committee - see page for list of meetings
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts

Thank you for saying yes to Measure S