Fixing Streets - Measure S

PCI Status, Jan 1, 2020

Pavement Condition Index (PCI) PCI of 66Pavement Condition Index (PCI) Status, as of Jan. 1, 2020

Measure P 2015 - 2019

Measure P Fourth Year Report

Fourth Year Report | PDF Version
Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Fixing Streets Measure S Sign


Week beginning
Feb. 24, 2020:

Active Engineering Projects Schedule
Please note: Schedule is subject to change.
  1. MEASURE S - Road reconstruction on-call contract -  Work through 3/1 at Veteran's Drive from Skyline to Yerba Buena and Via Del Rey from Yerba Buena to Herrmann Drive. Via Del Rey will be closed to through traffic but open to residents.
  2. Portola Plaza Sewer Lining & Trench Restoration - walkway concrete restoration left to complete - SEE MAP
  3. MEASURE S Sidewalk Repair, Phase 4 - Tree well protection filling left to complete in the New Monterey and Cannery Row areas. Little to no impact. SEE PLAN
  4. MEASURE S ADA Ramp Repair Here is a schedule of all upcoming locations for this project:  Del Rosa Ave. and N. Fremont 02/18 - 02/24; Alcalde Ave. and N. Fremont 02/24 - 03/02; Camino El Estero and Anthony St. 03/02 - 03/09; Del Monte and Park Ave. 03/09 - 03/16; Del Monte and Ocean Ave. 03/16 - 3/23. This schedule will be updated as changes occur.
  5. PG&E Gas Main Replacement - on Munras Avenue at the Casa Munras Hotel will temporarily close lanes and require traffic control. ONGOING (Non-City PG&E Project)
  6. Cal-AM Water Main Construction in Ryan Ranch - on Lower Ragsdale Drive at Highway 68 to Wilson, then down York Road and back to Highway 68. ONGOING PROJECT (Non-City Cal-AM Project)
  7. Cannery Row Parking Garage Elevator Enclosure - Work continues on site - no road closures. ALL NEARBY BUSINESSES REMAIN OPEN DURING CONSTRUCTION. Elevators will be closed through early April. Temporary parking of ADA accessible vehicles are near the exit with a walking exit to Hoffman. Signs direct vehicles with strollers towards more accessible areas. SEE CIP PROJECT PAGE (CIP)
  8. ONGOING FOR SEVERAL MONTHS - Maintenance Stairs Construction at Portola Walkway - 3/5 - set up at 8am and start the concrete placement at 9am. All equipment will be out of the turn around by noon and site cleaned; 4/6 - set up the crane at 8am to set the stairs. All equipment will be out of the turnaround by 3pm and site cleaned. - (MCC Maint Fund)
  1. ADA Ramp Repair at Del Monte and Alvarado St in front of Cibo's Restaurant - -Tentatively scheduled for 3/16 (Non-City Cal-AM Project)
  2. MEASURE S ADA Ramp Construction - on-call contract - Alvarado Street at Bonifacio, tentative start date of 3/9. SEE MAP
  3. MEASURE S Citywide Road Surface Repair Phase 2 - SEE LIST OF STREETS (subject to change) SEE THE LATEST PAVEMENT CONDITION INDEX (PCI) REPORT
  4. MEASURE S Citwide Road Surface Repair Phase 1 - Final slurry work in Skyline Forest will be postponed until early spring for proper weather/ temperature conditions. Phase 2 work details and list of streets will be ready and posted soon.
  5. Wayfinding Signage Project - prep work starting (CIP)
  6. Elk Run and Deer Forest Dr, and Mule Deer Way Resurfacing - Details coming soon. (NCIP)
  7. Pine and Hawthorne streets storm drain and bulb outs - Details coming soon. (NCIP)
  8. Montecito Park Phase 4 and Laguna Grande Park Improvements - Details coming soon. Tentatively starting in March (NCIP)

Caltrans to perform work on two major Monterey Peninsula arteries - Highway 68 and Highway 156 traffic will impacted over two days each next week. For more information on this project and for traffic updates on other Caltrans projects in Monterey County, call the District 5 Public Affairs Office at (805) 549-3318 or visit the website at dot.ca.gov/caltrans-near-me/district-5.

Measure S Tax Quick Facts

As of April 1, 2019 - Measure P is now Measure S

Thank you for saying yes to Measure S