Fixing Streets - Measure P

Streets Completed, as of Dec. 2017

Measure P Street Resurfacing Status Map Measure PProject Status Map, Dec. 2017

Fixing Streets Measure P Sign

Measure P Second Year Report

Second Year Report | PDF Version

First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
February 12:

Please note: The schedule is subject to change.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Montecito Park Entry and Seating Installation and Phase 2 Site Improvements Project (NIP and CDBG)
  • Recreation Trail Maintenance at 504 Wave and 48 Cannery Row. The Rec Trail will still be accessible during the work. (CIP)
  • Stuart Avenue closure to reshape top of the street where it meets Airport Road (Casanova Oak Knoll neighborhood) (NIP)
  • Three ADA Ramps at Casa Verde and Encina (Villa Del Monte neighborhood) - continuing into mid-Feb (NIP)
  • MEASURE P: ADA Ramp and Street Reconstruction Phase 5 - Work expected into early March in Old Town, specifically one block of Larkin Street and two blocks of Watson Street - street grinding and paving work complete - striping and other punchlist items this week - SEE MAP
  • Wharf II Pile Replacement & Repair - Critical repairs should be completed in March. (CIP)
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Crews will begin installation of the 36-inch pipeline at the Aguajito/Fremont intersection, Mon. - Fri., 7 AM to 5 PM. Traffic controls will be posted. One lane of Cypress Street from Withers to Hoffman in New Monterey will be closed mid-week for isolated paving work. Work on the Highway 68 pipe bridge will continue at Old Salinas Highway and Fairgrounds Road. No road closures are anticipated this week due to bridge construction. Permanent paving work will take place Wed. - Fri. on Munras Avenue and Fremont Street.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays through Fall 2018 - tentative days for concrete pours when Hoffman will be closed during the day and re-opened at the end of the work day: Wednesday, February 14;Tuesday, February 20; Tuesday, March 6

construction signs

Upcoming

  1. MEASURE P ADA Signaling Intersections, Phase 1 - coming in February
  2. Street light on Franklin at Calle P - Light ordered and work is scheduled for March. (Calle P Assessment District)
  3. North Fremont Bike and Pedestrian Access and Safety Improvement Project - Currently out to bid - learn more about this project: monterey.org/NFremontBikePed and sign up for email updates.

Ongoing

  • Cooper Molera Adobe State Historical Park, Polk and Munras (Non-City Project) This project may impact parking and traffic in the area at times. Expected completion in Spring 2018.
  • Van Buren Senior Housing Project Van Buren Senior Housing is the result of a partnership between the City of Monterey and MidPen Housing to bring much needed affordable senior housing to the city. Van Buren is ideally situated in downtown Monterey – only a short walk from parks, a library, a major regional transit center, a large grocery store, and various other amenities. Van Buren began construction in April 2017 and is expected to welcome residents in summer 2018.

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts