Fixing Streets - Measure P

Thank you for saying yes to Measure S

Streets Status as of Oct. 2018

Measure P Street Resurfacing Status Map Measure PStreets Status as of October 2018

Streets Status for 2015 - 2019

Measure P Street Resurfacing Status Map Measure PStreets Status Map, July 2018

Fixing Streets Measure P Sign

Measure P Third Year Report

Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Weeks beginning
MARCH 25, 2019:

Active Engineering Projects Schedule
Please note: Schedule is subject to change.
  1. Measure P Citywide ADA Ramps and Street Reconstruction Phase 7- 1: Drainage and street improvements at the intersection of Via Mirada and El Dorado. This will close the area to through traffic for up to two weeks. 2: Partial Reconstruction of Glenwood Circle. This is tentatively scheduled for early April.
  2. CR7 Parking Lot - lot at David/Irving/Foam - Phase 2 - Install stormwater filtration box - impacts 30 spaces during construction. (CIP)
  3. Cannery Row Parking Garage Elevator Enclosure This project has been moved to fall 2019 - (CIP)
  4. Madison Street ADA Ramps and Montecito Park Improvements, Phase 3 - Construction on Madison between Dutra and Van Buren. Van Buren at Madison intersection closed. Traffic control will be in place on Madison. (CDBG and NIP)
  5. Pacific Street Sidewalk, Phase 3 - Work on Pacific street at Via Arboles for sidewalk, retaining wall and tree work. Traffic control may be in place. Work will start after 8 a.m. SEE PLANS (NIP)
  6. Sewer Rehab pipe bursting - Pipe bursting underway (this process is noisy). SEE MAP | NEW 3 WEEK SCHEDULE ("What a Relief")
  7. Waterfront Parking Lot Upgrades - Work has moved to Phase 2 on the other side of the lot - reconfiguring, repaving, and added infrastructure including electric vehicle charging stations 3-WEEK SCHEDULE (CIP and Parking Fund)
  8. MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 2 - Work moves back to the Cunningham intersection at the entrance of NPS.
  9. North Fremont Bike and Pedestrian Access and Safety Improvement Project - MARCH UPDATE - N Fremont EB (toward Seaside) – lane tapers from 2 lanes to 1 lane at Dela Vina and again at Casanova; N Fremont WB (toward Monterey) – lane tapers from 2 lanes to 1 lane at Dela Vina – there is also MST traffic control at Hannon Ave for their Jazz stop work; Casanova @ N Fremont is open northbound ONLY (uphill toward Jiffy Lube).  For more information please see the FACT SHEET - NO WORK ON WEEKENDS. PLEASE SUPPORT AREA BUSINESSES. Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates
  10. Cal-Am Cannery Row waterline project: Main waterline installed and tested. Water lines to businesses will now be connected. Work hours are 8 AM to 5 PM weekdays. See Cal-Am letter for details (Non-City Project)

construction signs

Ongoing

  1. Waterfront Parking Lot Upgrades - Please check the CURRENT list (above) of projects for details.
  2. Measure P Citywide Street Resurfacing, Phase 7 - Final slurry deferred to April, 2019 due to scheduling and weather conflicts. Crews throughout Camino Aguajito, Camino El Estero, Del Monte Ave, and Pacific adding temporary markings. SEE MAP
  3. Solar Panels installation on the Monterey Conference Center - installation of 330 solar panels
  4. Monterey Bay Aquarium Education Center Construction - See recent San Jose Mercury News article  (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue. Completion expected late winter/early spring 2019.

Upcoming

  1. ADA Improvements and remodel of City Clerk's Office late April start date - (CIP)

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Measure P Oversight Committee - see page for list of meetings
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts