Fixing Streets - Measure S

Up next

Phase 2 Road Surface Repair coming next -
list of streets will be available in mid-December.

PCI Status, Oct. 2019

Pavement Condition Index (PCI) PCI of 66Pavement Condition Index (PCI) Status, Oct. 2019

Measure P 2015 - 2019

Measure P Fourth Year Report

Fourth Year Report | PDF Version
Third Year Report | PDF Version
Second Year Report | PDF Version
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Fixing Streets Measure S Sign


Week beginning
November 19, 2019:

Active Engineering Projects Schedule
Please note: Schedule is subject to change.
  1. Work on Madison and Pacific (non-City project) - MST will be doing some road work at Madison and Pacific streets, Tues., 11/19 and Wed., 11/20. Traffic control will be in place. Work hours are 8:30 a.m. to 3 p.m.
  2. MEASURE S Road Surface Repair Phase 1- Final slurry work in Skyline Forest will be postponed until early spring for proper weather/ temperature conditions. Phase 2 work details and list of streets will be ready and posted by mid December.
  3. Cannery Row Parking Garage Elevator Enclosure - Offsite steel fabrication work happening through mid December. Elevator on Wave Street side of garage will be closed for approximately 11 weeks for this project to improve the elevator system. Start date is 10/29/19, completion date is 2/21/20. Both elevators from 10/29/19 - 2/12/20. New, temporary parking of ADA accessible vehicles will be near the exit with a walking exit to Hoffman. Signs will direct vehicles with strollers towards more accessible areas. SEE CIP PROJECT PAGE - (CIP)
  1. MEASURE S Sidewalk Repair, Phase 4 - planned for a Dec start (MEASURE S)
  2. Wayfinding Signage Project (CIP)
  3. MEASURE S Street Improvements - Potholing on Mar Vista for future street repairs that will start in a few months.

CalTrans may be performing other work locally. Look up CalTrans construction.

Measure S Tax Quick Facts

As of April 1, 2019 - Measure P is now Measure S

Thank you for saying yes to Measure S