Fixing Streets - Measure P

Streets Status, July 2018

Measure P Street Resurfacing Status Map Measure PProject Status Map, July 2018

Fixing Streets Measure P Sign

Measure P Second Year Report

Second Year Report | PDF Version

First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
AUGUST 13:

Please note: The schedule is subject to change.
  • PG&E gas line installation on Madison Street Traffic control in place through 9/12/18, Mon through Thu, 7 AM to 5:30 PM - Madison St. from intersection of Van Buren St. to Pacific St. On Pacific St. From Madison St to Logan Ln.(Non-City Project)
  • Measure P Citywide ADA Ramps and Streets Reconstruction, Phase 7 - Fisherman's Flat Neighborhood - Work continues on ADA curbs and gutter installation at three intersections: Via Isola at San Vito, at Marsala, and at Trapani. Some detours for pedestrians.
  • Citywide sewer spot repairs - Work taking place 400 block of Pierce Street at Jefferson - see map- (sewer fund and "What a Relief")
  • North Fremont Bike and Pedestrian Access and Safety Improvement Project - Work over next 2 weeks: Casa Verde – SE corner - excavate large diameter traffic signal pole foundation & form for sidewalk/curb & gutter; Casa Verde  – NE corner - Place sidewalk & curb ramp Hannon – Concrete work for sidewalks & cross gutter both sides – continue closure; Casanova  – south side – grading and install storm drain – removing “free right” at this location.
    Impacts of work for week of Aug. 13: N Fremont EB – lane restrictions @ Casa Verde & Airport Rd N Fremont WB – lane restrictions @ Casa Verde Hannon Ave @ N Fremont closed – work on both corners and cross gutter Casanova NB – lane shift.
    Impacts of work for week of Aug. 20: N Fremont EB – lane restrictions @ Casa Verde & Airport Rd N Fremont WB – lane restrictions @ Casanova & Casa Verde Hannon Ave @ N Fremont closed – work on both corners and cross gutter Casanova NB – lane shift - Driveways to businesses are accessible.
    - Motorists will see steel trench plates in the roadway covering active work; plates are pinned in place so that they will not move.
    - Work shift 7:00 a.m. to 3:30 p.m. – crews will make every effort to be off the road by 3:30 p.m. each day.
    Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates
  • Measure P Citywide Street Resurfacing, Phase 6 - MAP | LIST OF STREETS Final markings completed after Car Week (Aug. 18 - 26) - no detours in effect
  • Measure P Citywide ADA Ramps and Streets Reconstruction, Phase 6 - Cal-Am work will continue on the 100 block. Once that is complete, the final coat of pavement will be done and the NIP-funded crosswalk will be next. Striping still pending on York Road and Perry Lane (Nightwork).
  • MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 1 - Low impact work continues in downtown.
  • 200- 300 block of English Avenue - Work continues to pour concrete curbs and gutters - 3-week schedule through September 3. (NIP)
  • Scholze Community Center parking lot- repaving project will not be accessible during this work - work anticipated through most of August.
  • Colton Hall ADA Improvements - work will impact parking in the Dutra lot - ten spaces currently blocked for construction of ADA parking spaces NEWS RELEASE (Grants, NIP and CIP)
  • Cal Am Monterey Pipeline Project (Non-City Project) - SCHEDULE through August 24 -also see www.watersupplyproject.org/

    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297

construction signs

Upcoming

  1. Breakwater Bathroom ADA Upgrades, Phase 2 - Work coming soon on adjacent parking spaces - (NIP)
  2. Solar Panels installed at Monterey Conference Center- fall
  3. Cal-Am Cannery Row waterline project to start after Labor Day - (Non-City Project)

Ongoing

  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays through Fall 2018.
  • Wharf II Pile Replacement & Repair - Critical repairs under wharf. (CIP)
  • Cooper Molera Adobe State Historic Park, Polk and Munras (Non-City Project) Permanent re-opening late-August - watch for details.
  • Van Buren Senior Housing Project - Van Buren Senior Housing is the result of a partnership between the City of Monterey and MidPen Housing to bring much needed affordable senior housing to the city. Construction is expected to be completed in July with phased move-ins starting in late June. Grand opening celebration being planned for fall 2018.

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Measure P Oversight Committee - see page for list of meetings
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts