Featured Projects

Getting around Monterey Car-Free!

monterey.org/car-free-monterey


Week beginning
June 24, 2019:

Active Engineering Projects Schedule
Please note: Schedule is subject to change.
  1. Gigling Road ADA Ramps - At the Arnhem and Parker Flats Cutoff roads intersections. Traffic may be impacted. (Presidio)
  2. West Parking Garage ADA Upgrades - Work my impact Tyler Street and lot entrance. (CIP)
  3. Glenwood Bus Stop and Crosswalk Improvement - Traffic impacts include one way traffic and some detours during work hours. Project will last until about mid-August. See page 42 - https://monterey.org/Portals/0/Reports/NIP/NIP-Manual-2016.pdf and Item 14, https://monterey.org/Portals/0/Reports/NIP/NIP-FY17-18-Approved-Projects.pdf (NIP)
  4. Sewer Rehab pipe bursting - The two remaining locations, Wharf 2 and the Munras onramp to Highway 1 South, will be done by the end of July. More details coming soon. ("What a Relief")
  5. North Fremont Bike and Pedestrian Access and Safety Improvement Project - Ramona intersection on track to finish by the end of June. Thank you for your continued patience while we complete this project. Latest summary of work - CREWS:
    - mobilized at the end of June last year so they are just coming up on a year of construction
    - lost an entire month of working days due to rain
    - encountered many unknown underground utility conflicts which required working around/relocating
    - have been working with PG&E coordinating work that they must do before they complete their work; PG&E's ability to provide crews was hampered by responding to storm damage during our weather events
    - are working as hard and fast as possible; including some weekends to try to make up time.
    For more information please see the FACT SHEET Learn more about this project: monterey.org/NFremontBikePed and sign up for email updates

construction signs

Ongoing

  1. None at this time

Upcoming

  1. MEASURE S Barnet Segal Lane Repaving Project
  2. MEASURE S Street Improvements - Potholing on Mar Vista for future street repairs that will start in a few months.
  3. Sewer Lining Project (Sewer CIP Repair Fund)
  4. Cannery Row Parking Garage Elevator Enclosure Scheduled for fall 2019 - (CIP)

CalTrans may be performing other work locally. Look up CalTrans construction.

Additional major projects information

Major Projects Completed in 2017 and 2018

Thank you for saying yes to Measure S