Featured Projects

Prepping for the 4th of July festivities

monterey.org/july4th

Week beginning
MAY 21:

Please note: The schedule is subject to change.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Breakwater Restroom ADA Upgrades - scheduled to be completed in late May - one external shower will remain operational and there will be a portable restroom available (CIP)
  • Cannery Row Parking Lot 7 ADA Upgrades - Cannery Row at David Avenue - half the lot will remain open at a time, scheduled to be completed in late May, but may run into early June
  • 200- 300 block of English Avenue - install new curbs, sidewalks, drains, and gutters- delays encountered due to utility conflict. PG&E service lines to be relocated. Work will continue in early June. (NIP)
  • Colton Hall ADA Improvements - work will impact parking in the Dutra lot - NEWS RELEASE (Grants, NIP and CIP)
  • MEASURE P Citywide Signalized Intersections ADA Upgrades Phase 1 - Impacting the following intersections: Pacific at Soledad; Pacific at El Dorado; Pacific at Jefferson; Pacific at Franklin; Franklin at Van Buren; Franklin at Monroe; and Del Monte at Tyler - CURRENT SCHEDULE
  • Montecito Park Entry and Seating Installation and Phase 2 Site Improvements Project (NIP and CDBG)
  • Stuart Avenue closure (Casanova Oak Knoll neighborhood) - last phase of work to be completed soon (NIP)
  • Wharf II Pile Replacement & Repair - Critical repairs under wharf. (CIP)
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Potholing and Pipe Installation will continue on Fairgrounds road from Old Salinas Highway to Garden Road. Traffic controls will be posted. Construction of Hwy 68 pipe-bridge, between Garden Road and Old Salinas Highway will continue. No road closures are anticipated this week due to the bridge construction.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays through Fall 2018

construction signs

Upcoming

  1. Measure P Citywide ADA Ramps and Streets Reconstruction, Phase 6 - Via Gayuba, York Road, Perry Lane, and Vets Park Campsite - early June start date
  2. Measure P Citywide Street Resurfacing, Phase 6 mid summer start date
  3. Citywide sewer spot repairs, includes David Avenue at Jessie Street- see map - (sewer fund and "What a Relief")
  4. Scholze Community Center parking lot- coming in June
  5. North Fremont Bike and Pedestrian Access and Safety Improvement Project - Contract awarded, late summer start date - learn more about this project: monterey.org/NFremontBikePed and sign up for email updates.

Ongoing

  • Cooper Molera Adobe State Historical Park, Polk and Munras (Non-City Project) This project may impact parking and traffic in the area at times. Expected completion in mid summer 2018.
  • Van Buren Senior Housing Project Van Buren Senior Housing is the result of a partnership between the City of Monterey and MidPen Housing to bring much needed affordable senior housing to the city. Van Buren is ideally situated in downtown Monterey – only a short walk from parks, a library, a major regional transit center, a large grocery store, and various other amenities. Van Buren began construction in April 2017 and is expected to welcome residents in summer 2018.

CalTrans may be performing other work locally. Look up CalTrans construction.

Please note: The Cooper Molera and Cal Am Pipeline are non-city projects. Cooper Molera artist rendering by Art Zendarski.

Videos about the Cooper Molera Project

Additional major projects information

Major Projects Completed in 2017

Interactive Map of Citywide Projects