Featured Projects

Week beginning
February 26:

Please note: The schedule is subject to change.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Montecito Park Entry and Seating Installation and Phase 2 Site Improvements Project (NIP and CDBG)
  • Stuart Avenue closure to reshape top of the street where it meets Airport Road (Casanova Oak Knoll neighborhood) (NIP)
  • MEASURE P: ADA Ramp and Street Reconstruction Phase 5 - Work expected into early March in Old Town, specifically one block of Larkin Street and two blocks of Watson Street - street grinding and paving work complete - striping and other punchlist items this week - SEE MAP
  • Wharf II Pile Replacement & Repair - Critical repairs should be completed in March. (CIP)
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Work will continue on Aguajito Road and on the Highway 68 pipe bridge at Old Salinas Highway and Fairgrounds Road in Monterey, Monday through Friday, 7 a.m. to 5 p.m. Traffic controls will be posted, including the Aguajito Road Detour. No road closures are anticipated this week due to the bridge construction.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays through Fall 2018 - tentative days for concrete pours when Hoffman will be closed during the day and re-opened at the end of the work day: no closures this week; next week: Monday, Feb. 26, utility work begins Feb. 27 through March 2.

construction signs

Upcoming

  1. MEASURE P ADA Signaling Intersections, Phase 1 - coming in February
  2. Street light on Franklin at Calle P - Light ordered and work is scheduled for March. (Calle P Assessment District)
  3. North Fremont Bike and Pedestrian Access and Safety Improvement Project - Currently out to bid - learn more about this project: monterey.org/NFremontBikePed and sign up for email updates.

Ongoing

  • Cooper Molera Adobe State Historical Park, Polk and Munras (Non-City Project) This project may impact parking and traffic in the area at times. Expected completion in Spring 2018.
  • Van Buren Senior Housing Project Van Buren Senior Housing is the result of a partnership between the City of Monterey and MidPen Housing to bring much needed affordable senior housing to the city. Van Buren is ideally situated in downtown Monterey – only a short walk from parks, a library, a major regional transit center, a large grocery store, and various other amenities. Van Buren began construction in April 2017 and is expected to welcome residents in summer 2018.

CalTrans may be performing other work locally. Look up CalTrans construction.

Please note: The Cooper Molera and Cal Am Pipeline are non-city projects. Cooper Molera artist rendering by Art Zendarski.

Videos about the Cooper Molera Project

Additional major projects information

Major Projects Completed in 2017

Interactive Map of Citywide Projects