Project Title |
City of Monterey Street
Reconstruction 2009 - Abrego, Munras, Soledad, and Eldorado
|
TYPE OF WORK:
Reconstruction of Street Segments |
FUNDING SOURCE:
Federal Grant |
CONTACT:
Capital
Projects Division
831.646.3997
(suggest@ci.monterey.ca.us) |
|
DESCRIPTION and PURPOSE OF PROPOSED CONSTRUCTION |
|
This
project is for furnishing all labor, equipment, and materials required
for the reconstruction of various street segments. Street segments to
be reconstructed will be on: Abrego, Munras, Soledad,
and Eldorado Streets. Also included is the installation
and rehabilitation of sewer mains, storm drain catch basin
reconstruction, and street lighting. In general, the work consists of:
reconstructing failed pavement on Abrego, Munras, Soledad, and Eldorado;
overlaying portions of Abrego, Munras, Soledad, and Eldorado;
constructing approximately 160 linear feet of 6” diameter sewer on
Abrego; sewer spot repairs; and lining approximately 1,237 linear feet
of 6” diameter clay sewer pipe and associated restoration of
improvements. |
SCHEDULED TIME FRAME
NOTE: The construction dates are
approximate and may vary due to weather or unforeseen conditions. |
| BEGIN: |
Sept. 14, 2009 |
| ESTIMATED
COMPLETION DATE : |
December 7, 2009 |
|
UPDATES/REVISIONS:
Press Release - Soledad Drive
Press Release - Abrego
Nov. 20, 2009 Press Release
|
|
TRAFFIC IMPACT |
|
Traffic will be impacted on Soledad
Drive, between Munras and Monte Vista, and Abrego and Munras from
Fremont to Don Dahvee. Please see press releases for more
information. |
|
|