Please ensure Javascript is enabled for purposes of website accessibility City of Monterey, CA

Construction News



Construction this Week

WEEKS BEGINNING APRIL 22 and 29, 2024 - PLEASE NOTE: SCHEDULE IS SUBJECT TO CHANGE.

  1. UPDATED APRIL 20, 2024 - MEASURE S and P Citywide Road Resurfacing Phase 4 - WORK HAPPENING APRIL 22 - MAY3: Work on Lighthouse Avenue will continue intermittently in the day. No night work is scheduled during this period. The City is working to minimize disruptions to both residents and businesses including traffic impacts and night time noise. Utility adjustments and striping removal work will take place. The day work will be 8 a.m. to 5 p.m. with one lane closure at a time. Lane closures will be moving and isolated to the areas where utility work is on-going. Striping started on Munras Avenue during the day, Mon., 4/15.
    DAY WORK - Southbound (SB) is toward Monterey; Northbound (NB) is toward Pacific Grove - Utility adjustments will happen during the day next week as follows:


    LIST OF STREET SEGMENTS FOR THE ROAD SURFACE REPAIR. Upcoming Road Rehabilitation, Winter 2023 and Summer 2024 - SEE MAP Upcoming Road Surface Repairs, Winter 2023 through 2025 - SEE MAP

  2. Measure S Citywide Road Surface Repair Project Phase 5 - Tues 4/23 and on Wed 4/24; Work on Figueora St from Del Monte up to the limits of work from the Marina Parking Lot (past the Dust Bowl Parking Entrance) to rehabilitate the pavement. They're doing this in two phases to maintain access. This will be the first operation, but they will need to come back and slurry seal it in May as well. SCHEDULE

    Scope of work: In general, the work consists of, but is not limited to, the demolition and construction of concrete curb, gutter, sidewalk, sidewalk crossings, pavement spot repair of approximately 266,193 SF, crack sealing, placing of approximately 1,017,463 SF of slurry seal Type II, associated striping removal and replacement, refreshing of existing painted street markings, traffic control and installation of necessary environmental pollution prevention requirements on various streets in the City of Monterey. Schedule | List of Streets Schedule A | List of Streets Schedule B
  3. Measure S Citywide Curb Ramps Project Phase 7 - This works is wrapping up in the next couple of weeks. Impacts are expected to be minimal. Scope of work: In general, the work consists of, but is not limited to, the demolition and construction of concrete curb ramps, gutter, and sidewalk on various streets in Old Town.  Schedule
  4. State Route 68: Olmsted Road: Thu., April 25 - The right shoulder along westbound State Route 68 at Olmsted Road will be closed for pavement repair work from 8 a.m. to 3:30 p.m. (Not a City Project)
  5. PG&E Monterey Substation Electrical Equipment Upgrade Fact Sheet - PG&E is working to upgrader their electrical equipment at the Monterey Substation (498 Del Monte Avenue - just across from the Harbor) An update on this project is coming soon. (Not a City Project)

Upcoming Projects

    1. Measure S and P Sidewalk spot repairs to clean up uplifts or other tripping hazards - long term throughout the city. Currently or soon in Old Town, New Monterey including Lighthouse Ave, and Cannery Row areas. A message from the Public Works Department: Pedestrian safety, and having a walkable community is of the utmost importance. Damaged or uplifted sidewalk can occur overtime, and the City of Monterey Public Works Department strives to perform repairs in a timely manner. If you notice orange paint on the sidewalk, it is an indication that a deficiency has been flagged and repairs are being coordinated.  The City continues to explore innovative methods to address minor sidewalk deficiencies and recently awarded a contract to contractor to diamond slicing uplifts in the Downtown and New Monterey Neighborhoods. Once these first neighborhoods are addressed, the contractor will continue to work in other neighborhoods throughout the City.

Active Projects


Q&A - HAVE A PUBLIC WORKS CONSTRUCTION-RELATED QUESTION? EMAIL SUGGEST@MONTEREY.ORG

Question: How do I report a raised sidewalk that has a potential to cause a tripping hazard?
Answer: If the uplift is caused by a city tree the city will fix it, otherwise it might be on the responsibility of the property owner or a utility company to address the issue. Typically, a Public Works crew will go out to identify the uplift, measure the uplift, paint the uplift and take pictures. We keep a log and send the appropriate party a letter to address the issue.