Fixing Streets - Measure P

Measure P Street Resurfacing Status Map Measure PProject Status Map, Aug. 2017

Fixing Streets Measure P Sign

Measure P Second Year Report

Second Year Report | PDF Version

First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
August 21:

Please note: Weather may cause possible delays or changes to the schedule.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Lower Presidio Historic Park Accessible Walkway up to the Sloat Monument (NIP)
  • Pearl Street Bridge Improvements - replace walk path - 85% complete (CIP)
  • 442 Casanova Avenue Sidewalk reconstruction, stump removal, curb and gutter ADA work - last week of work (CIP)
  • 300 Block of Belden Street Widening ON SCHEDULE - Week six - work is expected to finish in a week or so - SEE CONTRACTOR SCHEDULE AND NOTICE (NIP)
  • MEASURE P: ADA Ramp and Street Reconstruction Phase 4 - El Dorado Street between Major Sherman Road and Alta Mesa. Traffic will be impacted for about four weeks. Work will continue through October. SEE SCHEDULE - Pacific Street Exit from Lighthouse Avenue to close - SEE NEWS RELEASE FOR DETAILS (Measure P)
  • Veteran's Park Bocce Ball Court Contractor done; City crews still working on landscaping, signage, striping, other misc. (NIP)
  • Police Department Lobby Upgrades Work extended into week of Aug. 21, but the lobby should be reopened by Friday.
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Crews will continue pipeline construction in New Monterey on Lily Street. Additional curb, gutter, and sidewalk work will take place on Fairgrounds Road, and Fremont Street in Monterey.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Highway 68/Highway 1 Roundabout (monterey.org/hh68)
    Crews will focus on landscaping, installing additional signs, and completing the trench drain at the driveway to Carmel Hills Professional Center. No closures or detours are planned, but there will occasional shoulder closures for the signs to be installed and occasional flagging for the landscaping work. The Live Camera is Back! Take a look at the intersection in real time
    HH68 Roundabout May Take Longer
  • Monterey Bay Aquarium Education Center Construction (Non-City Project) Periodic and Brief Delays on Recreation Trail at Hoffman Avenue Weekdays, July 2017 to Fall 2018
    Days the contractor will be pouring cement, requiring trucks to unload adjacent to the building site and the closure of Hoffman Avenue, starting at 7:30 a.m. and finishing by 4:00 or 5:00 at latest: (Here's the schedule in PDF)
    • Tues., Aug. 22 and Wed., Aug. 23
    • Monday, August 28
    • Wednesday, September 6th
    • Thursday, September 14th

construction signs

Upcoming

  1. Wharf II Pile Replacement & Repair - Base job completed. Crews will return in September to complete additional work.(CIP)
  2. MEASURE P STORM DRAINS: Citywide Storm Drain Repairs Phase 3 - Soledad Drive at Soledad Place - potential road closure at times - dates still to be determined
  3. MEASURE P STREETS: Citywide Street Resurfacing/Slurry Phase 5 - starting in Sep MAP OF STREETS

Ongoing

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts