Fixing Streets - Measure P

Fixing Streets Measure P Sign

Measure P First Year Report
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning
June 26:

Please note: Weather may cause possible delays or changes to the schedule.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • MEASURE P STORM DRAINS: Citywide Storm Drain Repairs Phase 3 - next up - Soledad Drive at Soledad Place - potential road closure at times - dates still to be determined
  • MEASURE P STREETS: Citywide Street Resurfacing/Slurry Phase 4 Work in New Monterey/Cannery Row areas - See schedule NOTE: NEW MONTEREY SCHEDULE POSTPONED BY ONE DAY, CANNERY ROW SCHEDULE UPDATED AS FOLLOWS:
    Tuesday 6/27- Foam (Hoffman to Prescott) Wednesday 6/28 - Wave (Hoffman to Irving) Thursday 6/29 - Irving (Foam to Laine)
  • MEASURE P SIDEWALKS: Citywide Sidewalk Repair Phase 3 - See map and list of streets and dates
  • MEASURE P ADA: Citywide ADA Ramps and Street Reconstruction, Phase 3 - Sloat Avenue: Road closed Mon., June 26 through Fri., June 30. MONDAY: work between Ninth and 10th streets, then this section will open; TUES - FRI, closed from Ninth Street to Del Monte Avenue.
  • Wharf II Pile Replacement & Repair - Impacts to parking and traffic on the wharf. (CIP)
  • Veteran's Park Bocce Ball Court (NIP)
  • Police Department Lobby ADA improvements
  • Cal Am Monterey Pipeline Project (Non-City Project) - also see www.watersupplyproject.org/
    Paving work will wrap up on North Fremont Street and begin on High and Jefferson Streets in Monterey. Pipeline construction will also continue Madison Street.
    Have a question or concern? Call the CalAm project hotline at: (831) 646-3297
  • Highway 68/Highway 1 Roundabout (monterey.org/hh68)
    Day and Night work
    Thursday, June 22 – Tuesday, June 27 (Day and Night) Those leaving Pebble Beach from the Highway 1 Gate will be able to turn left to access Highway 68 ONLY. The southbound Highway 1 on-ramp will remain CLOSED for the duration. The Highway 1 Gate entrance to Pebble Beach will be OPEN. (Traffic will run on rough, unpaved road near the teardrop island). Wednesday, June 28 (Night: 8 p.m. – 6 a.m.) Night closure of southbound Highway 1 on-ramp, off-ramp, and the Pebble Beach Highway 1 Gate Gate entrance and exit will be CLOSED. The on-ramp and Highway 1 Gate will be OPEN during the DAY. (Traffic will run on rough, unpaved road near the tear drop island) Thursday, June 29 (Night: 8 p.m. – 6 a.m.) Night closure of the southbound Highway 1 on-ramp, off-ramp, and the Pebble Beach Highway 1 Gate entrance and exit will be CLOSED. The on-ramp and Highway 1 Gate will be OPEN during the day. During the southbound Highway 1 on-ramp closure, drivers coming from Pacific Grove, Community Hospital, and the Aguajito Road neighborhood who are going towards southbound Highway 1 (towards Carmel) will need to follow the signed detour and head north on Highway 1 to make a U-turn at Munras Avenue. Large trucks and busses are advised to U-turn at Aguajito Road. During the Pebble Beach Highway 1 Gate closures, drivers are advised to use an alternate gate. Sign Up for Text Message Alerts - Text 68roundabout to 888777

    Sign-up to receive email notifications: www.tamcmonterey.org. TAMC will send a weekly “look-ahead” with info about the construction, road closures, detours, traffic conditions and travel options.
    HH68 Roundabout May Take Longer

construction signs

Ongoing


Upcoming

  1. Lower Presidio Historic Park Accessible Walkway up to the Sloat Monument (NIP)
  2. ADA Ramp and Street Reconstruction Phase 4 on Littlefield, El Dorado and Pacific (Measure P) - July
  3. 300 Block of Belden Street Widening (NIP) - July
  4. Hawthorne Drainage Improvements - (CIP)
  5. Alvarado Street Light Replacement - 26 street lights between Bonifacio and Del Monte - July (CIP)
  6. Pearl Street Bridge Improvements, replace walk path - (CIP)
  7. MEASURE P STREETS: Citywide Street Resurfacing/Slurry Phase 5

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts