Fixing Streets - Measure P

Fixing Streets Measure P Sign

Measure P First Year Report
First Year Report | PDF Version

Measure P FAQs

$17.2 million for 728 street segments - A street segment is a portion of a street defined from intersection to intersection- basically each block. These streets were identified for inclusion by the City's pavement management system. The street listing was identified at Council meetings and actions that led to the justification for a ballot initiative.

$10.08 million for ADA upgrades - Federal Law requires City's to bring its facilities into compliance with the Americans with Disabilities Act (ADA) when it performs rehabilitation work to infrastructure (i.e. streets). Activities such as asphalt overlay or road reconstruction require that additional work be completed to bring accessory components (i.e. curb ramps) into compliance with current standards. Work such as pothole repair and slurry seals are considered maintenance and do not meet the threshold to mandate compliance.

$2.72 million for storm drain repair - Work has been identified to bring the lowest rated storm drain pipes into a state of good repair (approximately 5400 lf). Additional funding was identified to maintain storage ponds and replace pumping infrastructure.

$2 million for sidewalk repairs - Sidewalk work will be performed to repair the highest prioritized sidewalk displacement (type 3- displaced more than 3/4").

Downtown and Cannery Row

  • A majority of work downtown will occur spring 2016.
  • Paving operations will occur fall 2016.

Storm Drain Repair

  • Pipeline/pump work will be designed and constructed late summer 2015.
  • Other work will required additional environmental review - work will likely occur in 2017.

Sidewalk Repair

  • Sidewalk funding will augment the City's existing repair program. The City prioritizes work based upon number of pedestrians and displacement.

Traffic Calming Measures - The funding was identified to rehabilitate existing street infrastructure. Traffic calming does not fit in that description. Items such as bulb-outs at intersections will be 'driven' by the need to make ADA ramps compliant.

Curb and Gutter Repair - Functional curb and gutters will not be replaced even if it is not aesthetically pleasing.

Driveways - With vary minor exceptions, work on driveways will not occur (the exception is to meet compliance for an ADA corner ramp and there is a conflict with an existing ramp).

Neighborhoods - In general terms, work will occur on the eastern and western ends of the City and work will progress towards the center.

Street/ADA Work -

  • Street segments will be field evaluated to confirm the appropriate treatment.
  • Areas that are to receive maintenance work (slurry), will be packaged together for construction. The anticipation is that two slurry packages will go out each of the four years (spring and fall). It is very likely that the slurry work will occur on a City wide basis.
  • Areas to receive rehabilitation will be analyzed for ADA compliance.
  • ADA ramp design and construction will occur.
  • When compliance is achieved, a paving package will be prepared and work will occur. Paving work will likely be more concentrated to specific areas.

Thank You!

Fun Facts

Week beginning January 16, 2017: Please note: Weather may create possible delays or changes to the schedule.
Active Engineering Projects Schedule
MAP OF ALL PROJECTS
  • Citywide storm drain repairs - Measure P
    Via Pariaso between Hermann and Via Gayuba; Pacific at Whispering Pines
  • San Carlos Beach Park stairs
    This project should last three weeks pending weather; no shower access will be available during this project.
  • Library Reroof
  • Citywide ADA Ramps and Street Reconstruction, Phase 2 Only striping and Van Buren remediation remain.
  • Cal Am Monterey Pipeline Project - 3 week look-ahead schedule - also see www.watersupplyproject.org/
    Work is expected to stop through Wednesday due to rain. Installation of the new 36” Monterey Pipeline on Fairgrounds Road will continue Thursday, weather depending. Construction on Fairgrounds Road will mostly take place in the parking lanes, allowing traffic to continue in both directions. Construction on Madison Street between Larkin and Van Buren in Monterey is also scheduled to resume Thursday. Detours onto Jefferson Street will be posted. Residents who live in the affected sections of Madison should check with contractors on site to make arrangements for driveway access during construction. Parking will be limited in areas where construction is taking place between 7 a.m. and 5 p.m. Temporary water service interruptions will occur for residents in affected areas of Madison when water service lines are reconnected to the newly relocated water main. These interruptions are estimated to last between 30 to 45 minutes. Affected properties will be notified by door hangers. Crews will knock on doors to provide additional notice before interruptions take place.
  • Sewer Work - No Map for week of 1/16/17
    Heritage Harbor site near Recreation Trail (may impact parking lot at mouth of Wharf)
  • Highway 68/Highway 1 Roundabout (monterey.org/hh68)
    January 16 - January 20, depending on the weather, crews will continue working on the earth work, electrical work, and drainage work. Work will continue to be behind the concrete barriers and off the road way, and no daytime or nighttime closures are currently planned.
    Sign Up for Text Message Alerts - Sign up to receive text message alerts for the Holman Highway 68 Roundabout by texting 68roundabout to 888777Sign-up to receive email notifications: www.tamcmonterey.org. TAMC will send a weekly “look-ahead” with info about the construction, road closures, detours, traffic conditions and travel options.
    HH68 Roundabout May Take Longer

construction signs

Ongoing


Upcoming

  1. Citywide Sidewalk Repair - Measure P, Phase 3
  2. Wharf 1 (Fisherman's Wharf) Sewer Line Repair
  3. Veteran's Park Bocce Ball Court (NIP)
  4. Citywide ADA Ramps and Street Reconstruction, Phase 3 - Sloat and Airport
  5. Dennis the Menace Park Sidewalks http://gisags8.ci.monterey.ca.us/pub/cip/32N1421.pdf and http://gisags8.ci.monterey.ca.us/pub/cip/32N1339.pdf

CalTrans may be performing other work locally. Look up CalTrans construction.

Area Maps

The maps below show the Measure P projects scheduled by area

Measure-P-Interactive-Map
City-wide Interactive Map
MeasureP-Zone-1X
Zone 1 Map
MeasureP-Zone-2X
Zone 2 Map
MeasureP-Zone-3X
Zone 3 Map
MeasureP-Zone-4X
Zone 4 Map
MeasureP-Zone-5X
Zone 5 Map
  • Monday, February 23 at the Monterey Youth Center
  • Wednesday, February 18 at the Casanova-Oak Knoll Park Center
  • Wednesday, February 11 at the Council Chambers WATCH MEETING VIDEO-ON-DEMAND
  • Monday, February 9 at the Hilltop Park Center

Measure P Tax Quick Facts